题目
你的项目正在实施新 CRM,用以替换三套遗留销售工具。上线前八周,你从非正式渠道得知主要用户群体——销售运营团队正在重组;两位支持该项目的资深经理即将离任;新领导层表示要“重新评估优先级”。这些均未正式通知你。项目经理首先应该做什么?
Your project is implementing a new CRM that will replace three legacy sales tools. Eight weeks before go-live, you learn informally that the sales operations team, the primary user base, is being reorganised. Two senior managers who supported the project are leaving, and new leadership wants to "re-evaluate priorities". None of this was formally communicated. What should the project manager do FIRST?
选项
- A.Reach out directly to the new sales operations leadership to confirm continued support and re-validate requirements.
- B.Continue execution per the current plan, since no formal change has been communicated through governance.
- C.Escalate to the sponsor with a summary of the changes and recommend pausing project work until leadership re-confirms.
- D.Update the stakeholder register, reassess stakeholder engagement, and bring the changes to the sponsor with options for how to proceed.
解析
解析:组织变革会触发正式的相关方重估:更新登记册、重新评估参与程度,再向发起人提供选项。在正式信息尚未更新前就私下接触缺乏依据;直接建议暂停则跳过了发起人决策所需的分析。
Rationale:Organisational change triggers a formal stakeholder reassessment: update the register, re-evaluate engagement levels, then bring options to the sponsor. Informal outreach before the formal picture is current lacks a basis, and jumping straight to a pause recommendation pre-empts the analysis the sponsor needs.