识别相关方与登记册 · PMP 练习题解析

相关方管理 困难 People 人域 题号 PMP202611-207

题目

你的项目正在实施新 CRM,用以替换三套遗留销售工具。上线前八周,你从非正式渠道得知主要用户群体——销售运营团队正在重组;两位支持该项目的资深经理即将离任;新领导层表示要“重新评估优先级”。这些均未正式通知你。项目经理首先应该做什么?
Your project is implementing a new CRM that will replace three legacy sales tools. Eight weeks before go-live, you learn informally that the sales operations team, the primary user base, is being reorganised. Two senior managers who supported the project are leaving, and new leadership wants to "re-evaluate priorities". None of this was formally communicated. What should the project manager do FIRST?

选项

  1. A.Reach out directly to the new sales operations leadership to confirm continued support and re-validate requirements.
  2. B.Continue execution per the current plan, since no formal change has been communicated through governance.
  3. C.Escalate to the sponsor with a summary of the changes and recommend pausing project work until leadership re-confirms.
  4. D.Update the stakeholder register, reassess stakeholder engagement, and bring the changes to the sponsor with options for how to proceed.
正确答案:D

解析

解析:组织变革会触发正式的相关方重估:更新登记册、重新评估参与程度,再向发起人提供选项。在正式信息尚未更新前就私下接触缺乏依据;直接建议暂停则跳过了发起人决策所需的分析。 Rationale:Organisational change triggers a formal stakeholder reassessment: update the register, re-evaluate engagement levels, then bring options to the sponsor. Informal outreach before the formal picture is current lacks a basis, and jumping straight to a pause recommendation pre-empts the analysis the sponsor needs.

同考点练习题