移交前两周,运营团队表示尚未准备好支撑新系统。你本应更早做什么,现在又该做什么?
Two weeks before handover, the operations team says it is not ready to support the new system. What should you have done earlier, and what should you do now?
选项
- A.Hand over anyway as planned.
- B.Plan readiness and knowledge transfer with operations as part of the project, and now agree a short transition plan with them.
- C.Ask the project team to run operations forever.
- D.Delay handover with no plan.
解析
解析:过渡就绪应自规划阶段就纳入,以保证项目结束后效益延续。当下与运营共同确认清晰的过渡计划,可降低移交风险。
Rationale:Transition readiness should be planned from the start so benefits continue after the project. Now, a clear transition plan agreed with operations reduces handover risk.