题目
竞争对手推出了类似产品,市场调研显示你计划中的某个功能如今价值已很低。你应该怎么做?
A competitor launches a similar product, and market research shows one of your planned features now has little value. What should you do?
选项
- A.Build the feature anyway because it is in the plan.
- B.Review the business case with the sponsor and product owner and reprioritise or remove the feature.
- C.Speed up the team.
- D.Hide the research from stakeholders.
解析
解析:项目必须回应外部环境变化。复盘商业论证能让投入继续聚焦价值;照做已低价值的功能只是浪费资金。
Rationale:Projects must respond to external environment changes. Reviewing the business case keeps effort focused on value; building a now low-value feature wastes money.