题目
客户希望新仓库相较旧仓库降低碳足迹。你应如何处理?
Your client wants the new warehouse to cut its carbon footprint compared with the old one. How should you handle this?
选项
- A.Treat it as a nice-to-have and ignore it if costs rise.
- B.Include measurable sustainability criteria in the requirements, design and procurement decisions.
- C.Leave it to the construction contractor.
- D.Report on it only at the end of the project.
解析
解析:可持续性属于商业环境领域。将其量化并嵌入需求与供应商选择,才能让它从起点影响决策,而不是事后补记。
Rationale:Sustainability is part of the Business Environment domain. Making it measurable and embedding it in requirements and supplier selection ensures it shapes decisions from the start rather than being an afterthought.