商业环境与战略 困难 Business Environment 商业环境域 题号 PMP202611-190

题目

执行期间,没人清楚超过 1,000,000 的预算变更由谁审批,决策一再拖延。你应该怎么做?
During execution, nobody is sure who can approve budget changes above 1,000,000. Decisions keep getting delayed. What should you do?

选项

  1. A.Approve the changes yourself.
  2. B.Work with the sponsor to define governance, including decision rights and escalation thresholds.
  3. C.Stop all budget changes.
  4. D.Ask finance to decide every change.
正确答案:B

解析

解析:建立项目治理是商业环境领域的首要任务:明确决策权限与上报阈值能消除模糊、加快审批。自行批准则超越权限。 Rationale:Establishing project governance is the first Business Environment task: clear decision rights and escalation thresholds remove ambiguity and speed up approvals. Deciding yourself exceeds your authority.