题目
客户在电话中说最终交付物“看起来不错”。你接下来应该做什么?
The customer tells you in a call that the final deliverable "looks good". What should you do next?
选项
- A.Close the project immediately.
- B.Obtain formal acceptance as defined in the project plan or contract.
- C.Release the team and move on.
- D.Send the final invoice only.
解析
解析:口头认可不等于正式验收。正式签署既保护双方,也是收尾前的必要步骤,之后才解散资源并归档记录。
Rationale:Verbal approval is not formal acceptance. Formal sign-off protects both parties and is required before closing, after which resources are released and records archived.