题目
发起人刚刚批准了一个预测型办公楼建设项目的项目章程。你接下来应该做什么?
The sponsor has just approved the charter for a predictive office construction project. What should you do next?
选项
- A.Start construction work.
- B.Develop the integrated project management plan with key stakeholders.
- C.Sign contracts with all suppliers.
- D.Close the initiating phase report.
解析
解析:章程获批后项目进入规划阶段,需把范围、进度、成本、质量、风险等子计划整合为一份管理计划。执行与采购都应以该计划为依据展开。
Rationale:After the charter is approved the project enters planning, where scope, schedule, cost, quality, risk and other plans are integrated into one management plan. Execution and procurement follow from that plan.