进度计划制定与承诺 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-165

题目

发起人要你在明天的客户会议上承诺上线日期,而团队尚未完成估算。你应该怎么做?
The sponsor asks you to promise a go-live date in a client meeting tomorrow. The team has not estimated the work yet. What should you do?

选项

  1. A.Give the date the sponsor wants.
  2. B.Refuse to give any date.
  3. C.Work with the team to estimate quickly and give the sponsor a realistic forecast with options.
  4. D.Add a large buffer to a guessed date.
正确答案:C

解析

解析:基于团队的诚实估算才能维护信任与信誉。提供选项有助于发起人做出有依据的承诺;即便加了缓冲,拍脑袋猜测也不透明。 Rationale:Honest, team-based estimates protect trust and credibility. Giving options helps the sponsor make an informed promise; guessing, even with a buffer, is not transparent.