虚拟与分布式团队协作 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-156

题目

你的分布式团队每天只有两小时工作重叠时段,决策推进缓慢。你应该怎么做?
Your distributed team has only two overlapping working hours each day. Decisions are slow. What should you do?

选项

  1. A.Ask everyone to work the same hours as the head office.
  2. B.Work with the team to agree core collaboration hours and use shared tools for asynchronous updates.
  3. C.Hold all meetings at the time that suits you.
  4. D.Split the team into separate projects.
正确答案:B

解析

解析:约定核心协作时段并做好异步协作,既尊重每个人,也能让决策继续推进。强行统一时区会打击士气;把团队拆开对此问题并非合理对策。 Rationale:Agreeing core hours and good asynchronous practices respects everyone while keeping decisions moving. Forcing one time zone on everyone hurts morale; splitting the team is not justified by this problem.