管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-148

题目

你所在敏捷团队的两位资深开发人员就采用哪种架构发生激烈争论,已经拖慢了冲刺规划。你首先应该做什么?
Two senior developers on your agile team argue strongly about which architecture to use. The argument is slowing down sprint planning. What should you do first?

选项

  1. A.Escalate the matter to their functional manager.
  2. B.Choose the architecture yourself to save time.
  3. C.Meet both developers to understand their concerns and help them reach a solution together.
  4. D.Ask the whole team to vote immediately.
正确答案:C

解析

解析:以合作方式解决问题能触及根本原因并维护信任,长期效果最好。上报告状或独自拍板都会剥夺团队的主人翁感;匆忙投票则可能让其中一位专家并不认同结果。 Rationale:Collaborating to solve the problem gives the best long-term result because it addresses the root cause and keeps trust. Escalating or deciding alone removes ownership from the team, and a quick vote may leave one expert unconvinced.