团队建设与团队章程 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-149

题目

你正在组建一支混合型团队,成员分布在印度、波兰和美国。第一周就出现了关于响应时效和会议礼仪的误解。最好的做法是什么?
You are forming a hybrid team with members in India, Poland and the US. In the first week there are misunderstandings about response times and meeting etiquette. What is the best action?

选项

  1. A.Send everyone the company's HR policy.
  2. B.Facilitate a session where the team creates a team charter with working agreements.
  3. C.Set strict rules yourself and share them by email.
  4. D.Wait for the team to settle down naturally.
正确答案:B

解析

解析:由团队自己制定的团队章程能确立共同的基本规则并建立主人翁意识。由项目经理强加的规则往往难以被真正遵守,而放任等待会让小问题变大。 Rationale:A team charter created by the team sets shared ground rules and builds ownership. Rules imposed by the project manager are less likely to be followed, and waiting lets small problems grow.