资源管理 中等 People 人域 题号 PMP202611-146

题目

作为重组的一部分,公司从项目型组织转为职能型组织。项目经理担心团队成员因为现在向职能经理汇报,会对当前项目失去投入。项目经理应该怎么做?
As part of a restructuring effort, a company has transitioned from a projectized to a functional organization. The project manager is concerned that team members will become disengaged from the current project because they now report to a functional manager. What should the project manager do?

选项

  1. A.Work with the functional manager to assign goals related to the project to the team
  2. B.Advise the functional manager to ask the organization for additional resources as part of a mitigation plan
  3. C.Update the resource management plan with the organizational changes
  4. D.Meet the team and explain that organizational changes are transparent to the team
正确答案:A

解析

解析:在职能型组织中,职能经理掌握资源与考核权。项目经理通过协作把项目目标纳入成员的正式考核目标,使项目工作仍被认可与激励,从而在失去直接职权的情况下维持投入度。 Rationale:In a functional organization the functional manager controls resources and evaluations. By collaborating to embed project goals into team members' formal objectives, the PM keeps project work recognized and rewarded, sustaining motivation despite the loss of direct authority.