题目
一名新成员加入项目后,未能按项目特有的质量保证(QA)流程执行。项目经理事先应该怎么做才能避免这个问题?
A new team member joins the project and fails to apply the project-specific quality assurance (QA) processes. What should the project manager have done to avoid this issue?
选项
- A.Obtained external training in QA for the new team member
- B.Delegated QA tasks to the team lead
- C.Made sure the new team member understood all requirements
- D.Ensured the new team member had access to the quality management plan
解析
解析:质量管理计划是项目 QA 标准、工具与程序的权威来源。在新成员入职时确保其能获取并理解该计划,是最基础的预防措施;通用培训或委派 QA 都无法解决“不了解项目特定流程”的问题。
Rationale:The quality management plan is the definitive source of the project's QA standards, tools, and procedures. Ensuring new members can access and understand it during onboarding is the fundamental preventive step; general training or delegating QA does not address knowledge of project-specific processes.