题目
关于工作分解结构(WBS),以下哪项说法正确?
Which statement about the work breakdown structure (WBS) is true?
选项
- A.It is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish project objectives and create the required deliverables
- B.It is a simple list of project activities in chart form
- C.It is the same as the organizational breakdown structure (OBS)
- D.It is the bill of materials (BOM) needed to accomplish project objectives
解析
解析:WBS 将总范围工作层级分解为可管理的组成部分,界定项目完整范围;它不是活动清单、组织分解结构,也不是物料清单。
Rationale:The WBS hierarchically decomposes the total scope of work into manageable components and defines the total scope of the project. It is not an activity list, an OBS, or a bill of materials.