题目
责任分配矩阵(RAM)是:
The Responsibility Assignment Matrix (RAM) is:
选项
- A.Used to create the project budget and network diagrams
- B.Created at the activity level and used to tightly connect project roles and responsibilities to project network activities
- C.Used to show the relationships between work packages or activities and project team members, ensuring each work is assigned to only one person to minimize misunderstanding of responsibilities
- D.Used in individual performance assessments of project team members to establish accountabilities and duties
解析
解析:责任分配矩阵展示每个工作包或活动由哪些资源承担,并明确问责关系;它既不是预算工具,也不是用于个人绩效考核的。
Rationale:A RAM shows the project resources assigned to each work package or activity and clarifies accountability. It is not a budgeting tool, and its purpose is not individual performance appraisal.