题目
你所在组织承诺今年将碳足迹减少 20%。你的项目目前使用高排放设备。项目经理应该怎么做?
Your organization has committed to reducing its carbon footprint by 20% this year. Your project currently uses high-emission equipment. What should the project manager do?
选项
- A.Ignore the goal because the project started earlier
- B.Wait for instructions from the sponsor
- C.Evaluate the impact of switching to low-emission equipment and present findings to the sponsor
- D.Immediately replace all equipment
解析
解析:项目经理应先分析业务、成本与进度影响,再提出与组织可持续目标对齐的变更建议。
Rationale:The project manager should analyze the business, cost, and schedule implications before recommending changes to align with organizational sustainability goals.