结束采购流程的第一步是什么?
What is the first step in the Close Procurements process?
选项
- A.Pay the final invoice
- B.Verify deliverables were accepted according to the contract
- C.Archive procurement documentation
- D.Evaluate vendor performance
解析
解析:在结束采购之前,项目团队必须确认所有合同约定的可交付成果均已完成并通过正式验收。
Rationale:Before closing procurement, the project team must confirm that all contractual deliverables were completed and formally accepted.