题目
项目经理把两项原本顺序进行的活动改为同时进行,以缩短工期。这使用了什么技术?
A project manager shortens the schedule by running two sequential activities simultaneously. What technique is being used?
选项
- A.Crashing
- B.Resource Leveling
- C.Fast Tracking
- D.Critical Chain Method
解析
解析:快速跟进是把原本顺序执行的活动并行开展,从而在不改变范围的前提下压缩工期。
Rationale:Fast tracking overlaps activities that were originally sequential to reduce project duration without changing scope.