进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-050

题目

项目经理把两项原本顺序进行的活动改为同时进行,以缩短工期。这使用了什么技术?
A project manager shortens the schedule by running two sequential activities simultaneously. What technique is being used?

选项

  1. A.Crashing
  2. B.Resource Leveling
  3. C.Fast Tracking
  4. D.Critical Chain Method
正确答案:C

解析

解析:快速跟进是把原本顺序执行的活动并行开展,从而在不改变范围的前提下压缩工期。 Rationale:Fast tracking overlaps activities that were originally sequential to reduce project duration without changing scope.