相关方分析与权力利益方格 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-013

题目

在一次产品发布中,发起人期望发布时包含所有计划功能,市场部门希望发布提前,运营部门希望发布带来的问题尽可能少。你应该采取哪两项行动?(选择两项)
On a product launch, the sponsor expects every planned feature at launch. Marketing wants the launch date moved earlier. Operations wants the launch to cause as few problems as it can. Which two actions should you take? (Choose two.)

选项

  1. A.Group the stakeholders by power and interest to see whose needs shape the key choices.
  2. B.Facilitate a joint discussion so the groups can agree on priorities and trade-offs.
  3. C.Promise each group what it wants to keep everyone positive.
  4. D.Wait until the first release to see who complains.
  5. E.Email each group a copy of the schedule baseline.
正确答案:A,B

解析

解析:考纲要求对相关方分组、了解各方期望,并牵头促成共识。相互矛盾的承诺必然导致失败;等待或仅发文件都无法化解冲突。 Rationale:The ECO asks you to group stakeholders, learn what each one expects, and lead talks that bring them together. Making conflicting promises sets up failure. Waiting or sending a document does not resolve the conflict.