风险管理 困难 Process 过程域 题号 PMP202611-009

题目

案例:你管理一个安装新分拣线的混合项目。硬件工作按预测型计划执行,软件团队按两周迭代工作。此前已将供应商延误登记为风险,并约定应对措施:切换到已批准的备选供应商。电机安装活动有五天总浮动时间。现在输送带供应商通知电机将晚三周到货。你首先应该做什么?
Case: You manage a hybrid project to install a new sorting line. Hardware work follows a predictive plan; the software team works in two-week iterations. A supplier delay was logged as a risk with an agreed response: switch to an approved backup supplier. The motor installation activity has five days of total float. The conveyor supplier now says the motor shipment will arrive three weeks late. What should you do first?

选项

  1. A.Ask the sponsor for more budget to expedite the shipment.
  2. B.Have the risk owner carry out the agreed risk response and update the risk register.
  3. C.Cancel the contract and start a new procurement.
  4. D.Move the next software release earlier to fill the gap.
正确答案:B

解析

解析:该风险已经发生,且既定的应对措施已经存在。三周延误超过五天浮动时间,因此迅速执行可保护里程碑。同时应把它登记为问题,然后报告影响。 Rationale:The risk has now occurred, and a response already exists. A three-week delay exceeds the five days of float, so acting quickly protects the milestone. Log it as an issue as well, then report the impact.