题目
一名团队成员想把客户需求文档粘贴到免费的公共 AI 聊天机器人中,以便更快地起草用户故事。你公司目前还没有 AI 使用规定。你应该怎么做?
A team member wants to paste client requirement documents into a free public AI chatbot to draft user stories faster. Your company has no AI rules yet. What should you do?
选项
- A.Allow it because it saves time.
- B.Ban all AI tools on the project for good.
- C.Check the data rules with your governance and compliance contacts before anyone uses client data.
- D.Let each team member decide for themselves.
解析
解析:2026 版考纲通过真实场景把 AI 纳入考试。客户数据涉及安全与合规问题,因此必须先确认规则。未经分析就永久禁用,等于白白放弃有用工具。
Rationale:The 2026 outline brings AI into the exam through realistic scenarios. Client data raises security and compliance questions, so you confirm the rules first. A permanent ban throws away a useful tool without analysis.