进度压缩与赶工 · PMP 练习题解析

进度管理 中等 Process 过程域 题号 PMP202611-005

题目

在一个预测型的办公室装修项目中,关键路径上的一项电气检查延误了四天。发起人表示移交日期不能更改。你首先应该做什么?
On a predictive office fit-out project, an electrical inspection on the critical path slips by four days. The sponsor says the handover date cannot move. What should you do first?

选项

  1. A.Add electricians to every remaining activity.
  2. B.Check how the delay affects the plan, then look at ways to compress the schedule.
  3. C.Tell the sponsor that the handover date will slip.
  4. D.Skip the inspection and continue with the next activity.
正确答案:B

解析

解析:先分析再行动。明确影响后,才能比较快速跟进(并行开展任务)与赶工(增加人力并付出额外成本)。绝不应跳过强制性检查。 Rationale:Analysis comes before action. Once you know the impact, you can compare fast tracking (doing tasks in parallel) with crashing (adding people at extra cost). You should never skip a required inspection.