题目
在一个预测型的办公室装修项目中,关键路径上的一项电气检查延误了四天。发起人表示移交日期不能更改。你首先应该做什么?
On a predictive office fit-out project, an electrical inspection on the critical path slips by four days. The sponsor says the handover date cannot move. What should you do first?
选项
- A.Add electricians to every remaining activity.
- B.Check how the delay affects the plan, then look at ways to compress the schedule.
- C.Tell the sponsor that the handover date will slip.
- D.Skip the inspection and continue with the next activity.
解析
解析:先分析再行动。明确影响后,才能比较快速跟进(并行开展任务)与赶工(增加人力并付出额外成本)。绝不应跳过强制性检查。
Rationale:Analysis comes before action. Once you know the impact, you can compare fast tracking (doing tasks in parallel) with crashing (adding people at extra cost). You should never skip a required inspection.