题目
根据本次迭代的燃尽图,可以看出这次迭代处于什么状态?
Based on this iteration's burndown chart, what can be said about this iteration?

选项
- A.It is on track to be completed as planned.
- B.It is ahead of schedule.
- C.It is in jeopardy of not being completed as planned.
- D.It should be abandoned.
解析
解析:图中直线是理想燃尽线。实际曲线始终高于理想线,且从第 3 天起几乎不再下降,说明剩余工作量高于计划,按此趋势难以在本迭代内完成承诺范围,因此存在无法按计划完成的风险。
Rationale:The straight line is the ideal burn. The actual line stays well above it and flattens out from day 3 on, so work remaining is higher than planned and the iteration is unlikely to finish its committed scope on time.