敏捷度量:速率与燃尽 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-667

题目

根据本次迭代的燃尽图,可以看出这次迭代处于什么状态?
Based on this iteration's burndown chart, what can be said about this iteration?
根据本次迭代的燃尽图,可以看出这次迭代处于什么状态?

选项

  1. A.It is on track to be completed as planned.
  2. B.It is ahead of schedule.
  3. C.It is in jeopardy of not being completed as planned.
  4. D.It should be abandoned.
正确答案:C

解析

解析:图中直线是理想燃尽线。实际曲线始终高于理想线,且从第 3 天起几乎不再下降,说明剩余工作量高于计划,按此趋势难以在本迭代内完成承诺范围,因此存在无法按计划完成的风险。 Rationale:The straight line is the ideal burn. The actual line stays well above it and flattens out from day 3 on, so work remaining is higher than planned and the iteration is unlikely to finish its committed scope on time.