产品待办含 200 个事项,团队平均速率为每冲刺 20 个故事点。产品负责人问 Scrum Master 项目要多久。在不知道故事点总量的情况下,最恰当的回应是什么?
A product backlog contains 200 items. The team's average velocity is 20 story points per sprint. The Product Owner asks the Scrum Master how long the project will take. Without knowing the story point totals, what is the most appropriate response?
选项
- A.10 sprints: divide the number of stories by velocity.
- B.A meaningful forecast requires the backlog to be estimated in story points first. Offer to facilitate a backlog estimation session with the team and then calculate a range-based forecast.
- C.It is impossible to estimate in agile, the backlog will continue to grow.
- D.Give a rough estimate of 200 ÷ 20 = 10 sprints as a starting point.
解析
解析:B 正确。速率以故事点为计量单位,不是故事数量。故事复杂度差异极大:200 个各 1 点与 200 个各 10 点完全不同。预测必须先有故事点总量。Scrum Master 应给出通往有意义预测的路径,而不是一个无意义的数字。A、D 混淆了故事数量与故事点;C 错误——敏捷项目完全可以给出区间预测。
Rationale:B is correct. Velocity is measured in story points, not in number of stories. Stories vary enormously in complexity: 200 stories at 1 point each is completely different from 200 stories at 10 points each. A forecast requires story point totals. The Scrum Master should offer a path to a meaningful forecast rather than giving a meaningless number. Options A and D confuse story count with story points. Option C is incorrect: agile projects can and do provide range-based forecasts.