题目
某敏捷团队已运行 3 个冲刺,速率分别为 30、28、32 个故事点。用于计划目的,下个冲刺采用哪个速率最可靠?
An agile team has been operating for 3 sprints. Their velocity is 30, 28, and 32 story points. For planning purposes, what is the most reliable velocity to use for the next sprint?
选项
- A.32 - use the most recent sprint as the best indicator.
- B.30 - use the average of all three sprints for the most stable forecast.
- C.28 - use the lowest to build in safety margin.
- D.35 - use an optimistic estimate to motivate the team.
解析
解析:B 正确。多个冲刺的平均速率((30+28+32)/3 = 30)是统计上最可靠的预测值。单个冲刺易受假期、缺勤或故事难易波动影响,平均值能平滑这些差异。只看最近一冲刺(A)过度依赖单一数据点;取最低值(C)人为保守;用激励性数字(D)会作出不现实承诺、损害信任。
Rationale:B is correct. Average velocity over multiple sprints (30+28+32 ÷ 3 = 30) provides the most statistically reliable forecast. Individual sprints can be influenced by holidays, team absences or unusually easy/hard stories. The average smooths these variations. Using only the most recent sprint (A) overweights one data point. Using the lowest (C) introduces artificial conservatism. Using an aspirational number (D) creates unrealistic commitments and undermines trust.