题目
项目团队用 Stacey 复杂性模型定位不确定性程度,并据此选择项目生命周期。需求已被充分了解,但团队对实现所需的这项技术不熟悉,因此选择了自适应生命周期。
团队最可能把该项目定位在 Stacey 复杂性模型的哪个区域?
(真实考试中需在图上点选区域,本题请选择对应标号。)
A project team is using the Stacey Complexity Model to map the degree of uncertainty and select an appropriate project life cycle. Requirements are well known, but the team is unfamiliar with the technology needed to implement them, so the team selects an adaptive life cycle.
Where on the Stacey Complexity Model did the team most likely map the project?
(On the real exam you would click the correct area of the image; here select the matching label.)

选项
- A.A
- B.B
- C.C
- D.D
解析
解析:图的纵轴是需求不确定性、横轴是技术不确定性。需求清晰说明纵轴取值低,技术不熟悉说明横轴取值高,两点交汇落在区域 C。这类项目适合自适应或混合生命周期,与题干选择一致。
Rationale:Vertical axis is uncertainty of requirements, horizontal axis is technical degree of uncertainty. Requirements are clear (low on the vertical axis) while the technology is unfamiliar (high on the horizontal axis), which places the project in area C and calls for an adaptive or hybrid life cycle.