定量风险分析:EMV与决策树 · PMP 练习题解析

风险管理 中等 Process 过程域 题号 PMP202611-668

题目

发起人承诺修建一条从内陆城市 Azules 通往海岸的高铁,现有 Brazos 与 Corazon 两条备选线路。根据决策树中两条线路在高需求、低需求情形下的成本、概率与收益,Brazos 线路的期望货币价值是多少?
Your sponsor has committed to building a high-speed rail from the inland city of Azules to the coast. You have two possible routes, Brazos and Corazon. Given the costs, odds and rewards for high and low demand of each route in the decision tree, what is the expected monetary value of the route to Brazos?
发起人承诺修建一条从内陆城市 Azules 通往海岸的高铁,现有 Brazos 与 Corazon 两条备选线路。根据决…

选项

  1. A.1.6 billion
  2. B.-2 billion
  3. C.0.8 billion
  4. D.10.8 billion
正确答案:C

解析

解析:每条分支要先用“收益减去线路成本 10 亿”得到净路径价值,再加权求和:0.8 × (12 − 10) + 0.2 × (6 − 10) = 1.6 − 0.8 = 0.8,即 8 亿。 Rationale:Each branch must use the net path value (reward minus the route cost of 10 billion): 0.8 x (12 - 10) + 0.2 x (6 - 10) = 1.6 - 0.8 = 0.8 billion.