题目
项目经理正在收尾项目。下列哪项是项目收尾流程的最后一步?
A project manager is closing a project. Which of the following is the LAST step in the project closure process?
选项
- A.Obtain formal acceptance of deliverables from the customer.
- B.Close all procurement contracts with vendors.
- C.Conduct final lessons learned with the project team.
- D.Archive project documents and release resources to the organisation.
解析
解析:D 正确。收尾顺序大致是:取得客户验收(A)→ 关闭采购合同(B)→ 总结经验教训(C)→ 归档文档并释放资源(D)。归档与释放资源是最后的行政动作,标志项目组织正式解散。验收必须先于收尾活动;采购必须在最终结算前关闭;经验教训要在团队散伙前收集。
Rationale:D is correct. The closure sequence is roughly: obtain customer acceptance (A), close procurements (B), conduct lessons learned (C), then archive documents and release resources (D). Archiving and resource release is the final administrative act: the formal signal that the project organisation is disbanded. Acceptance must come before closure activities. Procurements must be closed before final accounting. Lessons learned should be captured before the team disperses.