WBS 与工作分解 · PMP 练习题解析

范围管理 中等 Process 过程域 题号 PMP202611-632

题目

你即将开始车辆制动系统某一工作包的工作,想在开工前查看验收标准。到哪里找?
You are about to begin work on a work package for a vehicle's braking system and want to review the acceptance criteria before starting. Where can you find this information?

选项

  1. A.Project management plan
  2. B.Activity attributes
  3. C.Requirements documentation
  4. D.The WBS dictionary
正确答案:D

解析

解析:WBS 词典是对 WBS 的补充,逐工作包给出工作描述、里程碑、质量要求与验收标准。 Rationale:The WBS dictionary supplements the WBS with detail per work package: description of work, milestones, quality requirements and acceptance criteria.