题目
你正在管理一个 1000 万美元的项目。就项目重新基准化而言,以下哪项是可接受的原因?
You are managing a $10 million project. For re-baselining the project, which of the following is an acceptable cause?
选项
- A.The client approved a scope addition with a $150,000 budget increase and a two-week extension of the scheduled completion
- B.The contractor's company instituted a quality assurance program and pledged to spend $1 million next year
- C.Design department productivity was lower than estimated, causing 1,000 additional hours and a forecast two-week delay
- D.The performing organization's engineering department converted to a new $250,000 CAD system
解析
解析:重新基准化需要经过批准的正式范围、成本或进度变更——本例中客户已批准增加范围并相应增加预算与工期。内部效率低下、供应商投入或工具升级都不属于获批的范围变更。
Rationale:Re-baselining requires an approved, authorized change to scope, cost, or schedule—here the client approved a scope addition with matching budget and time. Internal inefficiency, vendor investments, or tool upgrades are not authorized scope changes.