题目
你在做流程改进项目,已访谈相关方,摸清供应商、产品、制造步骤与输入输出。现在可以开始分析流程了,下一步应当做什么?
You are managing a process improvement project and have interviewed stakeholders to understand suppliers, products, manufacturing steps, and inputs and outputs. You are now in a good position to start analyzing the processes. What should you do next?
选项
- A.Determine the cost of conformance
- B.Determine the cost of non-conformance
- C.Use control charts to analyze the processes
- D.Create a SIPOC model
解析
解析:规划质量管理中,分析流程首先要可视化,用流程图类工具;SIPOC 正是把供应商、输入、流程、输出、客户串起来的那种图。
Rationale:In Plan Quality Management, visualizing processes starts with a data representation tool such as a flowchart; SIPOC maps suppliers, inputs, process, outputs and customers.