沟通技巧:倾听反馈与情商 · PMP 练习题解析

沟通管理 中等 Process 过程域 题号 PMP202611-283

题目

项目经理带领一支技术知识强于自己的专家团队。成员有时绕过项目经理,直接向相关方作出承诺。项目经理应该怎么做?
A project manager is managing a project with a team of subject matter experts who have more technical knowledge than the PM. Team members sometimes bypass the project manager and make commitments directly to stakeholders. What should the project manager do?

选项

  1. A.Work with the team to establish clear communication protocols in the communication management plan, clarifying which commitments require PM involvement and which team members can make directly.
  2. B.Remove the team members' stakeholder access to enforce the communication hierarchy.
  3. C.Accept the situation: expert teams should be allowed to communicate freely with stakeholders.
  4. D.Assert authority by reminding team members that all stakeholder communication must go through the PM.
正确答案:A

解析

解析:A 正确。解法是清晰且共识的沟通协议,而非命令控制。专家成员往往确实需要直接对接相关方,项目经理的价值在协调而非阻断。在沟通计划中界定哪些事项需项目经理知情,既不压制专家沟通,又避免口径不一致。单纯强调权威(D)在专家团队中引发反感;取消权限(B)过激且适得其反;完全放任(C)可能带来失控的范围承诺。 Rationale:A is correct. The solution is clear, agreed-upon communication protocols, not command-and-control restrictions. Expert team members often do need direct stakeholder access; the PM's value is in coordinating, not blocking. A communication plan that defines what requires PM visibility prevents misalignment without stifling expert communication. Pure authority assertion (D) breeds resentment in expert teams. Removing access (B) is disproportionate and counterproductive. Accepting it entirely (C) risks uncontrolled scope commitments.