题目
项目经理在晚上 11 点收到某成员消息,说自己不堪重负、无法按期完成交付物。项目经理首先应该怎么做?
A project manager receives a message from a team member at 11pm saying they are overwhelmed and cannot complete their deliverable on time. What should the project manager do first?
选项
- A.Ignore the message until morning since it is outside working hours.
- B.Acknowledge the message, reassure the team member, and schedule a conversation the next morning to understand the situation fully before deciding how to respond.
- C.Respond immediately with a plan to reassign the work to protect the schedule.
- D.Escalate immediately to the project sponsor since a deliverable is at risk.
解析
解析:B 正确。简短确认收到能让成员感到被听见,缓解当下的压力;但深夜消息不必在当晚解决全部问题。次日上午沟通才能完整了解情况、可行选项与成员状态。立即转派(C)在未了解前就动手;完全忽略(A)可能加剧成员焦虑;在弄清情况前上报发起人(D)为时过早。
Rationale:B is correct. A brief acknowledgement shows the team member they have been heard, which reduces immediate stress. However, a late-night message does not require full problem-solving at that hour. A morning conversation allows a proper understanding of the situation, the options available and the team member's wellbeing. Immediate task reassignment (C) jumps to action without understanding. Ignoring entirely (A) may worsen the team member's distress. Sponsor escalation (D) is premature before understanding the situation.