题目
项目经理必须向关键相关方传递坏消息:对方期待的一项交付物因未预见的技术问题将晚 6 周。这次沟通的最佳做法是什么?
A project manager must deliver bad news to a key stakeholder: a deliverable they were expecting will be 6 weeks late due to an unforeseen technical issue. What is the best approach to this conversation?
选项
- A.Deliver the news directly and promptly, explain the root cause clearly, present what options are available and what is being done to mitigate further delay: giving the stakeholder the information and agency they need to respond.
- B.Wait until a solution is in place before telling the stakeholder so as not to alarm them unnecessarily.
- C.Ask a senior team member to deliver the news on the PM's behalf.
- D.Send a written report so the stakeholder has time to process the information before discussing it.
解析
解析:A 正确。PMI 道德准则要求及时、诚实的沟通。坏消息尽早告知,附带背景与选项,才尊重相关方做出知情决策的能力——他们自己也有下游依赖要安排。重大消息只发书面(D)显得生硬且延迟了双向沟通;等到有方案(B)等于扣住了对方当下就需要的信息;让别人代讲(C)是回避沟通责任。
Rationale:A is correct. PMI's Code of Ethics requires timely, honest communication. Bad news delivered promptly with context and options respects the stakeholder's ability to make informed decisions. They may have their own dependencies to manage. A written report (D) can feel impersonal for significant news and delays the two-way conversation. Waiting for a solution (B) withholds information the stakeholder may need now. Delegation (C) is evasion of the PM's communication responsibility.