沟通管理 中等 Process 过程域 题号 PMP202611-569

题目

视频会议中,某成员发言时总站起来走动,离开画面并干扰他人。项目经理应当怎么做?
During video conferences, a team member frequently stands up and paces while speaking, disappearing from view and distracting others. What should the project manager do?

选项

  1. A.Do nothing, since all people are different and have the right to behave naturally
  2. B.Discreetly mention the behavior to the meeting participants and tell them to accept the behavior
  3. C.After the meeting is over, discuss the issue in private with the team member
  4. D.Update the team charter with a rule requiring all team member to stay seated during meetings
正确答案:C

解析

解析:这属于无意识的非语言沟通,已经影响会议效果。私下沟通既不让他难堪,又能提升其沟通能力。 Rationale:The behavior is subconscious non-verbal communication harming the meeting; a private conversation both spares embarrassment and develops the member's communication skills.