管理团队:绩效与冲突 · PMP 练习题解析

资源管理 中等 People 人域 题号 PMP202611-502

题目

某成员总是错过截止时间,但完成时质量很高。项目经理首先应当:
A team member consistently misses deadlines but produces high-quality work when finished. The project manager should FIRST:

选项

  1. A.Have a private conversation to understand the cause
  2. B.Issue a formal warning
  3. C.Remove them from critical path tasks
  4. D.Report them to HR
正确答案:A

解析

解析:私下沟通能在处罚前发现根因(超负荷、优先级不清、个人困难),也保住了信任与体面。 Rationale:A private conversation uncovers root causes (overload, unclear priorities, personal issues) before punitive action; it preserves trust and dignity.