题目
你接手了一支在上线失败后士气低落的团队。你的首要任务是:
You inherit a demoralized team after a failed release. Your FIRST priority should be to:
选项
- A.Immediately replan the schedule
- B.Replace the weakest members
- C.Add more process controls
- D.Rebuild psychological safety: acknowledge the past, listen, and reset clear goals
解析
解析:心理安全优先——害怕被追责的团队既无法从失败中学习,也无法好好发挥。
Rationale:Psychological safety comes first — a team that fears blame cannot learn from failure or perform well.