敏捷度量:速率与燃尽 · PMP 练习题解析

敏捷与混合实践 困难 Process 过程域 题号 PMP202611-497

题目

Scrum 中的速率衡量的是:
Velocity in Scrum measures:

选项

  1. A.The amount of work a team completes per sprint, used for forecasting
  2. B.Individual developer speed
  3. C.Lines of code written
  4. D.Hours worked
正确答案:A

解析

解析:速率是团队层面的吞吐量指标,用来预测未来冲刺的产能。 Rationale:Velocity is a team-level throughput measure used to forecast future sprint capacity.