管理相关方参与 · PMP 练习题解析

相关方管理 中等 People 人域 题号 PMP202611-469

题目

相关方参与在什么情况下最有效?
Stakeholder engagement is most effective when it:

选项

  1. A.Is continuous throughout the project life cycle
  2. B.Happens only at project close
  3. C.Is delegated entirely to the sponsor
  4. D.Occurs only when problems arise
正确答案:A

解析

解析:持续参与能让相关方保持认同与支持;时断时续只会带来意外与抵触。 Rationale:Continuous engagement keeps stakeholders aligned and supportive; sporadic engagement invites surprises and resistance.