题目
一位关键相关方直到执行阶段才被识别出来,现在提出重大变更要求。项目经理首先应该做什么?
A key stakeholder was not identified until the executing phase and now demands major changes. What should the project manager do FIRST?
选项
- A.Assess the impact of the requested changes through integrated change control
- B.Reject the changes as too late
- C.Immediately implement the changes
- D.Ask the sponsor to overrule the stakeholder
解析
解析:所有变更请求都要先经整体变更控制评估对范围、进度、成本与质量的影响,再作决定。
Rationale:All change requests must go through integrated change control to assess impact on scope, schedule, cost, and quality before any decision.