整体变更控制 · PMP 练习题解析

整合管理 中等 Process 过程域 题号 PMP202611-454

题目

一位关键相关方直到执行阶段才被识别出来,现在提出重大变更要求。项目经理首先应该做什么?
A key stakeholder was not identified until the executing phase and now demands major changes. What should the project manager do FIRST?

选项

  1. A.Assess the impact of the requested changes through integrated change control
  2. B.Reject the changes as too late
  3. C.Immediately implement the changes
  4. D.Ask the sponsor to overrule the stakeholder
正确答案:A

解析

解析:所有变更请求都要先经整体变更控制评估对范围、进度、成本与质量的影响,再作决定。 Rationale:All change requests must go through integrated change control to assess impact on scope, schedule, cost, and quality before any decision.

同考点练习题