职业道德与合规 中等 Business Environment 商业环境域 题号 PMP202611-322

题目

项目经理发现某供应商向一名负责评估供应商提案的团队成员赠送了贵重礼品,该成员尚未接受。项目经理应该怎么做?
A project manager discovers that a supplier has offered an expensive gift to a team member who is responsible for evaluating vendor proposals. The team member has not yet accepted. What should the project manager do?

选项

  1. A.Allow the team member to accept the gift if it is within the organisation's gift policy limits.
  2. B.Do nothing, the team member has not accepted and no harm has occurred.
  3. C.Advise the team member to decline the gift, report the supplier's behaviour through the appropriate procurement channel, and consider removing the supplier from the evaluation process to protect procurement integrity.
  4. D.Reassign the team member from vendor evaluation duties without explanation.
正确答案:C

解析

解析:C 正确。供应商向参与评估的成员赠送礼品,无论是否接受都构成利益冲突。PMI 道德准则要求主动处理利益冲突。送礼行为本身已损害采购公正,应当举报。等到接受后再处理(B)延误了对明确伦理问题的处置;默默调岗(D)未处理供应商行为;礼品政策限额(A)不适用于正在进行的采购活动。 Rationale:C is correct. An unsolicited gift from a supplier to an evaluating team member is a conflict of interest regardless of whether it is accepted. PMI's Code of Ethics requires addressing conflicts of interest proactively. The offer itself compromises procurement integrity and should be reported. Waiting until the gift is accepted (B) delays action on a clear ethical issue. Silent reassignment (D) doesn't address the supplier's behaviour. Gift policy thresholds (A) don't apply to active procurement situations.