项目经理发现,为满足客户激进的时间要求,拟议项目将迫使组织违反一项环境法规。正确做法是什么?
A project manager identifies that a proposed project would require the organisation to violate an environmental regulation to meet the client's aggressive timeline. What is the correct course of action?
选项
- A.Proceed quietly and prepare to manage any regulatory response if it comes.
- B.Seek the client's permission to violate the regulation since they are requesting the timeline.
- C.Proceed, the client relationship is more important than marginal compliance issues.
- D.Refuse to proceed as planned. Report the compliance issue to the appropriate organisational and legal authorities, and work to find a compliant alternative schedule or scope that meets legal requirements.
解析
解析:D 正确。PMI 道德准则要求遵守所有适用法律法规:客户关系或工期都不能成为违规的理由。项目经理必须拒绝按原计划执行、通过正规渠道上报,并寻求合法替代方案。客户“许可”(B)无效——客户无权授权违法;悄悄推进(A)等于共谋;客户关系(C)不能凌驾于法律合规。
Rationale:D is correct. PMI's Code of Ethics requires compliance with all applicable laws and regulations: no client relationship or timeline justifies a regulatory violation. The project manager must refuse to proceed as planned, escalate through proper channels, and find a lawful alternative. Client permission (B) is irrelevant: clients cannot authorise regulatory violations. Proceeding quietly (A) is complicity. The client relationship (C) cannot supersede legal compliance.