一位相关方施压,要求你把项目效益报得比证据支持的更乐观,以保住资金。你应该怎么做?
A stakeholder pressures you to report project benefits more optimistically than the evidence supports, to keep funding. What should you do?
选项
- A.Report the optimistic figures to protect the funding.
- B.Report optimistic figures now and correct them later.
- C.Avoid reporting benefits at all to sidestep the issue.
- D.Report benefits accurately and transparently, even if the picture is less favourable.
解析
解析:准确透明的汇报既维护诚信,也让组织基于真实信息决策。虚高或隐瞒都会误导决策者,并违反职业操守。
Rationale:Accurate, transparent reporting upholds integrity and lets the organisation decide on real information. Inflating figures or withholding them misleads decision-makers and breaches professional conduct.