职业道德与利益冲突 · PMP 练习题解析

职业道德与合规 困难 Business Environment 商业环境域 题号 PMP202611-041

题目

你发现一名团队成员与某供应商存在利益冲突。你应该怎么做?
You discover a team member has a conflict of interest with a vendor. What should you do?

选项

  1. A.Ignore it if the vendor provides good pricing
  2. B.Discuss it privately with the team member
  3. C.Ensure it is disclosed according to company policy
  4. D.Terminate the team member immediately
正确答案:C

解析

解析:合乎道德的领导要求透明,并按程序披露潜在的利益冲突。 Rationale:Ethical leadership requires transparency and proper disclosure of potential conflicts of interest.