题目

项目经理的上级要求其篡改项目状态报告,让项目在即将到来的高管评审中显得按计划进行。项目经理应该怎么做?
A project manager is asked by their manager to falsify a project status report to make the project appear on track for an upcoming executive review. What should the project manager do?

选项

  1. A.Comply with the manager's request since they have authority over the PM.
  2. B.Falsify the report but document the true status privately to protect themselves.
  3. C.Refuse to falsify the report, explain the PMI Code of Ethics requirement for honesty, and offer to help present the true status constructively with a recovery plan.
  4. D.Report the situation to the PMI ethics hotline immediately.
正确答案:C

解析

解析:C 正确。PMI 道德准则明确要求所有沟通保持诚实,不受管理压力影响。项目经理必须拒绝、说明理由,并提供建设性替代方案。照做(A)无论谁指使都违反准则;一边篡改一边私下记录(B)仍是违规;直接对外举报(D)跳过了应先做的当面拒绝。 Rationale:C is correct. PMI's Code of Ethics explicitly requires honesty in all communications, regardless of managerial pressure. The project manager must refuse, explain why, and offer a constructive alternative. Complying (A) violates the Code of Ethics regardless of who instructed it. Private documentation while falsifying (B) is still an ethics violation. Immediate external reporting (D) skips the direct refusal, which should always come first.