题目
你的组织正在所有项目中推行新的合规标准。作为项目经理,你的责任是:
Your organisation is adopting a new compliance standard across all projects. As project manager, your responsibility is to:
选项
- A.Wait for an auditor to tell you what to change.
- B.Assume the standard applies only to future projects.
- C.Understand how the standard applies to your project and ensure the work conforms.
- D.Delegate all compliance judgment to individual team members.
解析
解析:理解标准并确保符合,是项目经理在组织治理下的合规职责。等审计上门属于被动应对;把判断权下放到个人会造成合规不一致。
Rationale:Understanding and ensuring conformance is the PM's compliance duty under organisational governance. Waiting for an auditor is reactive; delegating judgment to individuals produces inconsistent compliance.