题目
在指导委员会评审中,财务总监询问项目的数据处理是否符合内部客户数据政策、是否与行业治理框架一致、是否满足监管合规要求。下列哪项陈述正确区分了这三个概念?
During a steering committee review, the CFO asks whether the project's data handling meets internal policy on customer data, aligns with industry governance frameworks, and satisfies regulator compliance requirements. Which statement correctly distinguishes these three concepts?
选项
- A.Policy, governance and compliance all mean essentially the same thing in a project context.
- B.Policy is internal organisational rules, governance is the framework for decision-making and oversight, compliance is meeting external regulatory requirements.
- C.Governance is internal, policy is external, compliance is the project manager's responsibility.
- D.Compliance and governance are interchangeable; policy is a subset of both.
解析
解析:政策是组织内部规则,项目必须在其框架内运作;治理是决策、监督与权限的框架(发起人、指导委员会、变更控制委员会);合规是满足外部强加的法律、法规与标准。项目通常需同时满足三者,因此必须区分清楚。
Rationale:Policy is internal organisational rules the project must operate within. Governance is the framework of decision-making, oversight and authority (sponsor, steering committee, change control board). Compliance is meeting externally imposed laws, regulations and standards. A project usually must satisfy all three, which is why the distinctions matter.