定义范围与范围说明书 · PMP 练习题解析

范围管理 中等 Process 过程域 题号 PMP202611-112

题目

关于项目范围说明书,以下哪项说法不正确?
Which statement about the project scope statement is NOT true?

选项

  1. A.It is an output of the Validate Scope process
  2. B.It describes in detail the project's deliverables and the work required to create them
  3. C.It provides a common understanding of project scope among stakeholders
  4. D.It may contain explicit scope exclusions that help manage stakeholder expectations
正确答案:A

解析

解析:项目范围说明书是定义范围过程的输出,而不是确认范围的输出。其余关于其内容与用途(包括明确排除项)的描述均正确。 Rationale:The project scope statement is an output of Define Scope, not Validate Scope. The other statements correctly describe its content and purpose, including explicit exclusions.