活动排序与网络图 · PMP 练习题解析

进度管理 简单 Process 过程域 题号 PMP202611-100

题目

紧前关系绘图法(PDM)的定义是:
The precedence diagramming method (PDM) is defined as:

选项

  1. A.A method in which activities are represented by nodes and connected by one or more logical relationships to show the sequence in which activities are performed
  2. B.A scheduling technique that uses a probabilistic approach
  3. C.A time-phased graphical depiction of the arrow diagramming method showing durations and dependencies
  4. D.A method more accurate than the critical path approach when activity durations are unknown
正确答案:A

解析

解析:PDM 以节点表示活动,并用逻辑关系(FS、SS、FF、SF)连接,形成进度模型,展示工作顺序。它既不是概率技术,也不是箭线图法的图形变体。 Rationale:PDM builds the schedule model by representing activities as nodes and linking them with logical relationships (FS, SS, FF, SF) to show the sequence of work. It is not a probabilistic technique, nor a variant of the arrow diagramming method.

同考点练习题