题目
紧前关系绘图法(PDM)的定义是:
The precedence diagramming method (PDM) is defined as:
选项
- A.A method in which activities are represented by nodes and connected by one or more logical relationships to show the sequence in which activities are performed
- B.A scheduling technique that uses a probabilistic approach
- C.A time-phased graphical depiction of the arrow diagramming method showing durations and dependencies
- D.A method more accurate than the critical path approach when activity durations are unknown
解析
解析:PDM 以节点表示活动,并用逻辑关系(FS、SS、FF、SF)连接,形成进度模型,展示工作顺序。它既不是概率技术,也不是箭线图法的图形变体。
Rationale:PDM builds the schedule model by representing activities as nodes and linking them with logical relationships (FS, SS, FF, SF) to show the sequence of work. It is not a probabilistic technique, nor a variant of the arrow diagramming method.