沟通管理 中等 Process 过程域 题号 PMP202611-035

题目

一位相关方对项目进展表示不满。项目经理应该怎么做?
A stakeholder expresses dissatisfaction with project progress. What should the project manager do?

选项

  1. A.Add more resources immediately
  2. B.Schedule a meeting to align expectations
  3. C.Inform them the project is within baseline limits
  4. D.Send the latest status report again
正确答案:B

解析

解析:直接沟通有助于澄清期望、化解误解,避免过早升级问题。 Rationale:Direct communication helps clarify expectations and resolve misunderstandings before escalating concerns.